Locust Water Main and Storm Sewer Completed. Linden Water Main On-Going.

Work Performed
·         Storm sewer installation along Locust Avenue from Magnolia Street to Maple Street
·         Testing of newly installed water main along Locust Avenue
·         Grind In-place of existing pavement along Linden Avenue
·         Started water main installation along Linden Avenue

Work anticipated to be performed, July 30th to August 3rd
·         Complete water main installation along Linden Avenue
·         Perform testing of newly installed water main on Linden Avenue
·         Begin storm sewer installation along Linden Avenue
·         Begin water service replacements along Locust Avenue

Thanks again for all your patience as you deal with construction in your neighborhood.