 Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.
The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.


Thanks again for all your patience and understanding throughout the construction project. We hope that you are happy with the improvements made.


If you have any questions or concerns, please feel free to contact Tim Schwister, Village Project Manager, at 847-904-4422.

Thursday, October 11, 2018

Work Performed
Milled Locust
Prepped and tack coated Locust and Linden in advance of paving
Punch list completed

 

Work anticipated to be performed, October15 th to October 19.


 
  • Tentative for Monday surface on Locust and Linden.
  • Project  will be final
Thanks again for all your patience as you deal with construction in your neighborhood

Friday, October 5, 2018

Work Performed
Landscaping on Linden and Locust completed Thursday of this week
No work today due to Rain

 

Work anticipated to be performed, September 8th to September 12th.


  • Tentative for Monday is milling on Locust. Weather permitting
  • Tentative for Tuesday surface on Locust and Linden 
Thanks again for all your patience as you deal with construction in your neighborhood

Friday, September 21, 2018

Work Performed
Completed trench patching on Locust this week.
Working on Landscaping on Locust and Linden

 

Work anticipated to be performed, September 24th to September 28th.

·    Excavate, stone and fine grade on Linden weather permitting.
  • Tentatively pave Binder late next week.
  • Manhole frame adjustments on Linden.
  • Landscaping on both roads. weather permitting
 
Thanks again for all your patience as you deal with construction in your neighborhood

Friday, September 14, 2018

Work Performed

·        Removed and Replace dcurb on Locust and Linden

 

Work anticipated to be performed, September 17th to September 21st,

·    Locust Ave will have the Tranches paved by the end of the week weather permitting
  • Linden Ave. Fine grade the stone and pave Binder. Weather permitting
  • Manhole frame adjustments on Linden.
  • Landscaping on both roads. weather permitting
 
Thanks again for all your patience as you deal with construction in your neighborhood

Sunday, September 9, 2018

Work Performed

·        Storm sewer ongoing

 

Work anticipated to be performed, September 10th to September 14th

·    Storm sewer tentatively finishing early the week of September 10, 2018
  • The contractor will start prepping for curb and excavation work next week
  • There will be temporary lane closures the next two weeks to accommodate the  curb remove and replace and Excavation.
 
Thanks again for all your patience as you deal with construction in your neighborhood.
 

Friday, August 31, 2018

Work Performed

·        Storm sewer ongoing

 

Work anticipated to be performed, September 4th to September 7th

·    Storm sewer is anticipated to be finished the end of next 
  • The contractor will tentatively start prepping for curb and excavation work near the end of next
  • There will be temporary lane closures the next two weeks to accommodate the storm sewer and curb remove and replace.
 
Thanks again for all your patience as you deal with construction in your neighborhood.
We are wishing everyone a safe and enjoyable weekend

      Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information...