Friday, September 14, 2018

Work Performed

·        Removed and Replace dcurb on Locust and Linden

 

Work anticipated to be performed, September 17th to September 21st,

·    Locust Ave will have the Tranches paved by the end of the week weather permitting
  • Linden Ave. Fine grade the stone and pave Binder. Weather permitting
  • Manhole frame adjustments on Linden.
  • Landscaping on both roads. weather permitting
 
Thanks again for all your patience as you deal with construction in your neighborhood

      Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information...