Work Performed
· Storm sewer ongoing
Work anticipated to be performed, September 10th to September 14th
· Storm sewer tentatively finishing early the week of September 10, 2018
- The contractor will start prepping for curb and excavation work next week
- There will be temporary lane closures the next two weeks to accommodate the curb remove and replace and Excavation.
Thanks again for all your patience as you deal with construction in your neighborhood.