Friday, July 27, 2018

Locust Water Main and Storm Sewer Completed. Linden Water Main On-Going.

Work Performed
·         Storm sewer installation along Locust Avenue from Magnolia Street to Maple Street
·         Testing of newly installed water main along Locust Avenue
·         Grind In-place of existing pavement along Linden Avenue
·         Started water main installation along Linden Avenue

Work anticipated to be performed, July 30th to August 3rd
·         Complete water main installation along Linden Avenue
·         Perform testing of newly installed water main on Linden Avenue
·         Begin storm sewer installation along Linden Avenue
·         Begin water service replacements along Locust Avenue

Thanks again for all your patience as you deal with construction in your neighborhood.

Saturday, July 21, 2018

Locust Avenue Water Main and Storm Sewer On-Going

Work Performed
·         Water main installation along Locust Avenue from Magnolia Street to Maple Street

Work anticipated to be performed, July 23rd to July 27th  
·         Perform the necessary testing of the water main along Locust Avenue
·         Perform storm sewer installations along Locust Avenue
·         Grind In-place existing pavement along Linden Avenue in preparation for underground utility construction.
·         Depending on work progress, begin water main installation along Linden Avenue
 

Several residents are likely aware of the poor condition of the existing water main along Locust Avenue. The existing water main is being replaced due to its condition. Unfortunately during work this week, the existing water main did break several times causing unscheduled water main shut-downs. We are doing everything possible to ensure the new main is placed into service as quickly as possible to avoid further water main breaks and unscheduled shut-downs.

Thanks again for all your patience with the scheduled and unscheduled disruptions to your water service.

Sunday, July 15, 2018

Water Main Installation On-Going

Work Performed
·         Water main installation along Locust Avenue at Magnolia Street

Work anticipated to be performed, July 16th to July 20th
·         Continue with water main installation along Locust Avenue from Magnolia Street to Maple Street
·         Begin performing the necessary testing of the water main along Locust Avenue
·         Start underground utility improvements along Linden Avenue.
 
Heavy construction has started along the project site. Traveling through the neighborhood is getting increasingly more difficult. Thank you again for all your patience and understanding.

      Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information...