Friday, September 21, 2018

Work Performed
Completed trench patching on Locust this week.
Working on Landscaping on Locust and Linden

 

Work anticipated to be performed, September 24th to September 28th.

·    Excavate, stone and fine grade on Linden weather permitting.
  • Tentatively pave Binder late next week.
  • Manhole frame adjustments on Linden.
  • Landscaping on both roads. weather permitting
 
Thanks again for all your patience as you deal with construction in your neighborhood

      Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information...