Friday, September 21, 2018

Work Performed
Completed trench patching on Locust this week.
Working on Landscaping on Locust and Linden

 

Work anticipated to be performed, September 24th to September 28th.

·    Excavate, stone and fine grade on Linden weather permitting.
  • Tentatively pave Binder late next week.
  • Manhole frame adjustments on Linden.
  • Landscaping on both roads. weather permitting
 
Thanks again for all your patience as you deal with construction in your neighborhood

Friday, September 14, 2018

Work Performed

·        Removed and Replace dcurb on Locust and Linden

 

Work anticipated to be performed, September 17th to September 21st,

·    Locust Ave will have the Tranches paved by the end of the week weather permitting
  • Linden Ave. Fine grade the stone and pave Binder. Weather permitting
  • Manhole frame adjustments on Linden.
  • Landscaping on both roads. weather permitting
 
Thanks again for all your patience as you deal with construction in your neighborhood

Sunday, September 9, 2018

Work Performed

·        Storm sewer ongoing

 

Work anticipated to be performed, September 10th to September 14th

·    Storm sewer tentatively finishing early the week of September 10, 2018
  • The contractor will start prepping for curb and excavation work next week
  • There will be temporary lane closures the next two weeks to accommodate the  curb remove and replace and Excavation.
 
Thanks again for all your patience as you deal with construction in your neighborhood.
 

      Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information...