Friday, August 31, 2018

Work Performed

·        Storm sewer ongoing

 

Work anticipated to be performed, September 4th to September 7th

·    Storm sewer is anticipated to be finished the end of next 
  • The contractor will tentatively start prepping for curb and excavation work near the end of next
  • There will be temporary lane closures the next two weeks to accommodate the storm sewer and curb remove and replace.
 
Thanks again for all your patience as you deal with construction in your neighborhood.
We are wishing everyone a safe and enjoyable weekend

      Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information...